Hi,

I just looked into it and it looks like an inconsistency in the gerrit 
database. The latest builds branch points to a set of changes that are in 
staged state, while the change that is in integrating change is not in that 
branch. I've found the build branch that had the integrating change and 
rejected the change (and staged it again).

It appears that the change was staged Friday morning and nobody noticed it 
during Friday. Then came a long weekend, with Monday off and Tuesday also off 
in Norway.

Simon
________________________________________
From: Development <development-bounces+simon.hausmann=qt...@qt-project.org> on 
behalf of Thiago Macieira <thiago.macie...@intel.com>
Sent: Monday, May 16, 2016 10:42:32 PM
To: development@qt-project.org
Subject: [Development] dev CI integration stuck for 3½ days

Will someone PLEASE look into the qtbase/dev integration?

https://codereview.qt-project.org/156523 has been integrating for (at the time
of writing this email) 84 and a half hours -- 3.5 days -- and that's including
two full working days in Finland, one in Germany and Norway as today is is a
bank holiday in those countries. I believe we'll break the record by the time
someone gets around to fixing this, if we haven't yet.

Let's not hope we have to wait until after tomorrow's holiday in Norway for it
to get back to working.

--
Thiago Macieira - thiago.macieira (AT) intel.com
  Software Architect - Intel Open Source Technology Center

_______________________________________________
Development mailing list
Development@qt-project.org
http://lists.qt-project.org/mailman/listinfo/development
_______________________________________________
Development mailing list
Development@qt-project.org
http://lists.qt-project.org/mailman/listinfo/development

Reply via email to