There are four things left to be completed before we can release the new site:

#  Item                  Owner    Completion Estimated time
---------------------------------------------------------------
1. complete the design   Allan    90%        about one week
2. fine-tune the search  Bill     90%        about one week
3. work on the content   ???      70%        need help here
4. logo graphics         Jonathan ???        ???

We still didn't hear what happens to the winner log/buttons and the requested change to insert the '_' as in JAm_pH. Jonathan?

Please start looking at the content and see what should be fixed. This is about the content's readability by humans (grammar/typos/flow) and machines (HTML/CSS compliency).

The latest release (including the working search) is here:
http://perl.apache.org/preview/modperl-docs/dst_html/index.html

So if we get the logo issue resolved asap, we should be able to make the site's preview somewhere in the middle of the next week.

I suggest the following plan:

1. when the 4 items are completed we announce the preview URL at the users list and invite people to search for bugs and send content patches. Let's give this process about 2 weeks. During these 2 weeks we should automate all the build process and move the build environment on apache.org from my home dir to a place where all others with commit access can use it.

2. Once the review process is completed we replace the old site with the new one and announce the new site worldwide.

__________________________________________________________________
Stas Bekman            JAm_pH ------> Just Another mod_perl Hacker
http://stason.org/     mod_perl Guide ---> http://perl.apache.org
mailto:[EMAIL PROTECTED] http://use.perl.org http://apacheweek.com
http://modperlbook.org http://apache.org   http://ticketmaster.com



---------------------------------------------------------------------
To unsubscribe, e-mail: [EMAIL PROTECTED]
For additional commands, e-mail: [EMAIL PROTECTED]



Reply via email to