I don't know how different the map editors are between SI and GSW but this 
works for GSW:

arrdate = #dtm_date <<days (5); //adds 5 days to the #dtm_date to compute the 
arrdate

Hope this helps.

Bob Scheuermann



---- swarnkar_mahendra <[email protected]> wrote: 
> Hi,
>     I am working on SI's map editor version 5.4. 
>     I need to apply a logic to add 5 working days to the requested 
>     delivery date . Is there any logic that can add 5 working days to 
>     the given date.
> 
>     Any kind of help is highly appreciated.
>     Thanks
> 



------------------------------------

...
Please use the following Message Identifiers as your subject prefix: <SALES>, 
<JOBS>, <LIST>, <TECH>, <MISC>, <EVENT>, <OFF-TOPIC>

Job postings are welcome, but for job postings or requests for work: <JOBS> IS 
REQUIRED in the subject line as a prefix.Yahoo! Groups Links

<*> To visit your group on the web, go to:
    http://groups.yahoo.com/group/EDI-L/

<*> Your email settings:
    Individual Email | Traditional

<*> To change settings online go to:
    http://groups.yahoo.com/group/EDI-L/join
    (Yahoo! ID required)

<*> To change settings via email:
    [email protected] 
    [email protected]

<*> To unsubscribe from this group, send an email to:
    [email protected]

<*> Your use of Yahoo! Groups is subject to:
    http://docs.yahoo.com/info/terms/

Reply via email to