Nicolas Goaziou <m...@nicolasgoaziou.fr> writes:
>
> This raises another question, though. What is a reasonable behaviour for
> bulk schedule+log?

I can think of three reasonable options:

1. Prompt for a note, then apply it to all affected items.
2. Prompt for a note, then apply it only to items that are already
   scheduled (and hence rescheduled).
3. Don't attempt to add a note and just add timestamps.

Then there's the unreasonable option:

4. Prompt for a note for each item.

If I had to pick, I'd go with 2, but any of 1-3 is fine.  In this case,
having bulk scheduling work is more important than whether
org-log-reschedule is being faithfully applied, in my opinion.

Allen

Attachment: signature.asc
Description: PGP signature