On May 21, 2010, at 4:51 PM, Rainer Stengele wrote:
Hi all!
Creating clocktables for each day of a month is an excellent feature
in org!
Problem for me is that many resulting tables have a total time of
0:00.
The problem is not really the zero time I spent but the appearance
of the tables with zero total time.
Is there a possibility to skip getting such tables?
Rational: I do not need to show my boss or customer days where I
spent 0:00 time on the project.
Hi Rainer,
if you pull, you can now do
:stepskip0 t
in the definition line for the report.
HTH
- Carsten