"Sebastien Vauban" <wxhgmqzgwmuf-genee64ty+gs+fvcfc7...@public.gmane.org> writes:
> I want to compute efforts given in days. As explained by the doc of > `org-effort-durations', we must add a =d= modifier to tell Org that given > numbers > must be multiplied by 480 (in the case of hours) to get the correct number of > corresponding minutes. > > I did that, but (as shown in the following inlined ECM): > > - the computed total for task A is interpreted as hours (4.5 days becomes > 4 hours 30 minutes). > > - the grand computed total for all tasks becomes completely wrong (4:38 > instead of 4.5 + 0.125 = 4.625 days). > > Am I doing something wrong, or forgetting something? This should be fixed now. Thanks, -- Bastien