Christian Egli <christian.e...@sbs.ch> writes: > In theory (according to the doc string of > `org-taskjuggler--build-project') you should also be able to set an > "end" property on the project, but this hasn't been implemented yet.
I remember now what the problem with this was. The exporter uses the top task both as the task and the container for the project[1]. So an start and an end on this task applies to both the project and the task (which is not always what you want). You might want to assign a start to the top task but probably not an end. The end is supposed to be calculated based on efforts and resource availability. But unless you specify a default duration you will have to specify and end date for the _project_. Maybe we need some fake (in the sense that they are not tj3 attributes) attributes to specify start and end of a project. Thanks Christian Footnotes: [1] Unless you set `org-taskjuggler-keep-project-as-task' to nil -- Christian Egli Swiss Library for the Blind, Visually Impaired and Print Disabled Grubenstrasse 12, CH-8045 Zürich, Switzerland