Hello, John Hendy <jw.he...@gmail.com> writes:
> I ran into an error with a 30min task which used the :effort: property > to set this duration. Upon compilation, I noted the warning: > ``` > file.tjp:10: Warning: 400.0d of effort of task one does not fit into > the project time frame. > Warning: 1 tasks could not be scheduled > ``` > > I looked at the .tjp file, and 30min had been converted to 4800.0 > hours. I was able to reproduce with the following setup: > > #+begin_src min-config > (add-to-list 'load-path "~/.elisp/org.git/contrib/lisp/") > (require 'ox-taskjuggler) > #+end_src > > emacs -Q M-x load-file ~/path/to/min-config > > #+begin_src tj-time-test.org > > * Project :taskjuggler_project: > ** task1-effort-min > :PROPERTIES: > :start: 2014-11-01 > :effort: 30min > :allocate: jwhendy > :END: > ** task2-duration-min > :PROPERTIES: > :duration: 30min > :allocate: jwhendy > :blocker: previous-sibling > :END: > > #+end_src > EFFORT is a special property in Org (i.e., it is not specific to taskjuggler). It expects "HH:MM" format. So, you should set it to :Effort: 00:30 Regards, -- Nicolas Goaziou