All the elements that belong to Joe (listed in section 2 below), except 156281, have been committed to CVS.
Cheers,
Ricardo Balduino
Senior Software Engineer
IBM - RUP Team | EPF Committer
www.ibm.com/rational
www.eclipse.org/epf
| Per Kroll/Cupertino/IBM
09/22/2006 07:47 AM |
|
Hi,
i would like to cover the following topics for the PM meeting today (unfortunately, I will only be able to attend 30 min, and will have no internet access)
1) I have made suggestions for changes to Chris A' mtrl on Status Assessment, see attachments, with associated updates to bugzilla, see
| 151782 | Mon 09:58 | nor | P3 | PC | RESO | EPF | Content | 1.0 | --- | PM - Task: Assess Results - review content |
| 151821 | Mon 08:53 | nor | P3 | PC | RESO | EPF | Content | 1.0 | --- | PM - Work Product: Status Assessment - review content |
| 151837 | 10:25:10 | nor | P3 | PC | RESO | EPF | Content | 1.0 | --- | PM - Template: Status Assessment - create |
| 146463 | Mon 09:39 | maj | P2 | PC | RESO | EPF | Content | 1.0 | 1.0 M4 | PM - Guideline: Status Assessment - update content |
[attachment "Template - Status Assessment_pkr.doc" deleted by Ricardo Balduino/Cupertino/IBM] [attachment "Task Assess Results pkr.doc" deleted by Ricardo Balduino/Cupertino/IBM] [attachment "Status Assessment Guideline pkr.doc" deleted by Ricardo Balduino/Cupertino/IBM] [attachment "Artifact Status Assessment pkr.doc" deleted by Ricardo Balduino/Cupertino/IBM]
A) We need to agree on what we are doing, since I see a lot of changes recommended. If we agree on what we do, I can update CVS this PM (EST), so it makes it into todays build. But note that there are very important things we need to agree on, such as what this task does relative to Manage Iteration, whether we need the guidelines (I do not think so), etc
B) We must get this looked down into CVS today, see A).
2) We need to understand where Joe is at. This is what is in Bugzilla
| 156608 | 2006-09-10 | min | P3 | PC | NEW | EPF | Content | 1.0 | --- | PM: Plan the Project -- Don't use the term "kill" |
| 156281 | 2006-09-07 | nor | P3 | PC | ASSI | EPF | Content | 1.0 | 1.0 RC1 | PM - Elements Not Referenced in Task: Plan the Project |
| 146444 | 2006-09-01 | enh | P3 | PC | RESO | EPF | Content | unspe | --- | PM - Add new Example: Project Plan |
| 151828 | 2006-09-14 | nor | P3 | PC | RESO | EPF | Content | 1.0 | --- | PM - Guideline: Assign Changes to an Iteration - update c... |
| 146438 | 2006-09-14 | maj | P2 | PC | RESO | EPF | Content | 1.0 | 1.0 M4 | PM - Concept: Phase - Update content |
| 146456 | 2006-09-01 | maj | P2 | PC | RESO | EPF | Content | 1.0 | 1.0 M4 | PM - Guideline: Plan Project Phases - add content |
| 146504 | Mon 21:29 | maj | P2 | PC | RESO | EPF | Content | 1.0 | 1.0 M4 | PM - Template: Project Plan - replace |
| 147968 | 2006-09-07 | maj | P2 | PC | RESO | EPF | Content | 1.0 | 1.0 M5 | PM - Capability Pattern initiate_project - create content |
| 151424 | Mon 16:22 | maj | P1 | PC | RESO | EPF | Content | 1.0 | 1.0 M5 | PM - Review content of Project Manager role |
| 151426 | Mon 16:52 | maj | P1 | PC | RESO | EPF | Content | 1.0 | 1.0 M5 | PM - create content for plan_the_project task |
| 151829 | Mon 11:31 | nor | P3 | PC | VERI | EPF | Content | 1.0 | --- | PM - Report: Project Burndown - create |
| 151423 | 2006-09-07 | maj | P1 | PC | VERI | EPF | Content | 1.0 | 1.0 M5 | PM - Create content for artifact Project Plan |
I notice that
| 151829 | Mon 11:31 | nor | P3 | PC | VERI | EPF | Content | 1.0 | --- | PM - Report: Project Burndown - create |
is in Verified, yet, CVS is empty. This is not acceptable. Also, Joe says he has asked Ricardo to update a lot of stuff in CVS. We need to be clear on what staus is and what shold be reviewed.
3) I am now almost done with all of my PM stuff. Scott will provide feedback over the weekend on
| 151830 | 08:11:04 | nor | P3 | PC | RESO | EPF | Content | 1.0 | --- | PM - Report: Iteration Burndown - create |
and then I close it. <Kurt is OK with closing>
As soon as the bug in RC1 is resolved so I can use a new build (expected today), I will implement
| 147967 | 2006-09-06 | maj | P2 | PC | ASSI | EPF | Content | 1.0 | 1.0 M5 | PM - Capability Pattern assess_and_plan_iteration - creat... |
| 147969 | 2006-09-10 | maj | P2 | PC | ASSI | EPF | Content | 1.0 | 1.0 M5 | PM - Capability Pattern manage_iteration - create content |
which will require updates to 6 CPs (all 4 iteration CPs are impacted).
I am discussing with Jim what is left to do on
| 156283 | Wed 16:47 | nor | P3 | PC | VERI | EPF | Content | 1.0 | 1.0 RC1 | PM - Elements Not Referenced in Task: Plan Iteration |
if any, but that should be close to done.
I have an hour of work left on
| 151784 | 23:22:40 | nor | P3 | PC | RESO | EPF | Content | 1.0 | --- | PM - Task: Initiate Iteration - review content |
and then I will send for re-review. Should be done hopefully today or over the weekend.
All my other bugs are Closed.
4) Other PM bugs requiring attention?
Thanks
Per Kroll
STSM, Manager Methods: RUP / RMC
Project Lead: Eclipse Process Framework
Rational Software, IBM Corp
408-342-3815
_______________________________________________ epf-dev mailing list [email protected] https://dev.eclipse.org/mailman/listinfo/epf-dev