Hi,

In one of the previous calls it was suggested that we had available a 
tabular-format report from Bugzilla so we could see what bugs are assigned 
to what milestones and to what people.
I ran such a report and found out that not all practices have bugs 
assigned to the target milestones as we agreed to a while ago (1.5 M1 - 
1.5 M5). The report is showing only 34 out of 85 bugs are correctly 
assigned to one of the 5 milestones available for the current release.

See report here:
https://bugs.eclipse.org/bugs/report.cgi?x_axis_field=bug_status&y_axis_field=assigned_to&z_axis_field=target_milestone&query_format=report-table&short_desc_type=anywordssubstr&short_desc=&classification=Technology&product=EPF&component=Content&component=Website&target_milestone=1.5+M1&target_milestone=1.5+M2&target_milestone=1.5+M3&target_milestone=1.5+M4&target_milestone=1.5+M5&long_desc_type=allwordssubstr&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&emailtype1=substring&email1=&emailtype2=substring&email2=&bugidtype=include&bug_id=&votes=&chfieldfrom=&chfieldto=Now&chfieldvalue=&format=table&action=wrap&field0-0-0=noop&type0-0-0=noop&value0-0-0=

And flat list of work here:
https://bugs.eclipse.org/bugs/buglist.cgi?query_format=advanced&short_desc_type=anywords&short_desc=ID%3A+2LPP%3A+RVL%3A+WT%3A+CM%3A+TDD%3A+ED%3A+EA%3A+SV%3A+UCDD%3A+AT%3A+CI%3A+OpenUP%3A+%5BPracLib%5D&classification=Technology&product=EPF&component=Content&long_desc_type=allwordssubstr&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&emailtype1=substring&email1=&emailtype2=substring&email2=&bugidtype=include&bug_id=&votes=&chfieldfrom=&chfieldto=Now&chfieldvalue=&cmdtype=doit&order=Reuse+same+sort+as+last+time&known_name=PM+Practices&query_based_on=PM+Practices&field0-0-0=noop&type0-0-0=noop&value0-0-0=

I'd encourage practice owners to check their practices for consistency 
with what the team discussed and agreed to, so we have better visibility 
of performed vs remaining work.
Thanks for your understanding.

Ricardo.