Hi all,

Next week is the milestone week for *4.16M1*.

*Monday*: Last day of development (and even then, no "big changes"). After
Monday 18:00 ET, no feature work or unrelated fixes are allowed -- only
regression fixes.

*Tuesday*: All-day test pass. Nobody should develop or fix anything.
Literally spend the entire day testing.

*Wednesday*: Fix day with a focus on fixing regressions found during the
test day (Tuesday). No unrelated fixes. Review and thoroughly test all
commits.
* The last Wednesday build is the release candidate every team signs off on
Thursday.
* The "New and Noteworthy" entries are due on Wednesday evening:
Git repo: ssh://git.eclipse.org/gitroot/www.eclipse.org/eclipse/news.git
Gerrit: ssh://git.eclipse.org:29418/www.eclipse.org/eclipse/news.git
Live website: https://www.eclipse.org/eclipse/news/4.16/

*Thursday*: Sign-off after re-testing, or at least confirming no changes
have been made to your component's code since the last time the component
was tested well.

*Friday*: Build is officially declared and made available.
* The master branch stays closed until the milestone is officially
released. (That is, it is not enough that your component has signed off.)

Many thanks,
Mat
_______________________________________________
equinox-dev mailing list
equinox-dev@eclipse.org
To unsubscribe from this list, visit 
https://www.eclipse.org/mailman/listinfo/equinox-dev

Reply via email to