We are scheduled to promote and contribute 4.23 RC2 to SimRel on Friday, March 
4.

Don't forget to consult the endgame plan regarding release candidates:
https://www.eclipse.org/eclipse/development/plans/freeze_plan_4_23.php

Here is the schedule:
March 2 Wed 18:00 ET Release Candidate 2 build
March 3 Thu 1-day test pass against RC2 and sign-off
March 4 Fri Submit RC2 to release train

Please note the following excerpt from the freeze plan:

RC2
Release candidate containing fixes for the majority of known outstanding 
defects that we intend to fix for 2022-03 (4.23). At the end of RC2 build, 
there should not be any open defects tagged 4.23. All fixes submitted must have 
a project lead or PMC vote on the bug report, and the fix must be reviewed by 
an additional committer (any committer other than the one who made the fix). A 
positive review from a project lead or PMC member means implicit approval and 
no vote is needed on the bug report. Ongoing changes to documentation, tests or 
examples do not require approval.

Note: Master branch is open for 4.23 RC2 contributions.

Regards,
Kit Lo
Eclipse Babel Project Lead
IBM Eclipse SDK (IES) Technical Lead and Release Manager
_______________________________________________
equinox-dev mailing list
equinox-dev@eclipse.org
To unsubscribe from this list, visit 
https://www.eclipse.org/mailman/listinfo/equinox-dev

Reply via email to