I keep getting confused about how we handle these.  So we won't  
complete a task this iteration so I want it scheduled for next  
iteration.

Can I just change the "iteration05" to "iteration06" or does that  
screw up the run rate calculations and the such?  I think we only add  
the time spent on tasks completed, right?  This is what I've been  
doing previously but Allison wasn't sure about this being the right  
process.

Thanks!