Hello,

The Clean Up Parade is moving on ahead, and we are coming to an end (time wise) but are still in the middle of a lot of changes.

With that said, we need to extend Clean Up by an additional day. After which we'll have 4 days of testing and then 2 days to release.

This means that the release will be pushed back an additional day.

New Dates for the release

Clean Up Parade: ends March 31

Testing: April 1 - 6

Release: April 8

Thanks
Justin