Thanks everyone for your votes and responses! Here's what I'd like to do for 
the release schedule:

- Friday, June 29: cut release branch
  - Rel. Mgr. to backport critical bugfix/build/doc changes between branch and 
release
- Monday, July 9: begin release vote

Note that this a bit more conservative than the 2-3 week release schedule I 
originally mentioned (but not by much). As suggested, I've marked the wishlist 
items through JIRA as Blocker tickets. However, since these JIRAs are in 
varying stages of completion, I propose that anything that misses the deadline 
will need to be pushed to the next release (even if it's marked as a Blocker).

Here is a JIRA link to the list of v1.2.0 Blocker tickets: 
http://s.apache.org/1eH

Please raise any issues or concerns right away. Here's to putting out a great 
1.2.0 release!

Best,
Mike


PS: These were the wishlist items I saw that were raised in the discuss thread:
- Cannot start agent a 3rd time when using FileChannel 
<https://issues.apache.org/jira/browse/FLUME-1232>
- Remove the org.apache.hadoop.io (http://org.apache.hadoop.io).* dependencies 
from FileChannel and ResumableMemoryChannel 
<https://issues.apache.org/jira/browse/FLUME-1285>
- Add more unit tests for HBase sink 
<https://issues.apache.org/jira/browse/FLUME-1204>
- Create metric collection infrastructure 
<https://issues.apache.org/jira/browse/FLUME-748>
- Support external tooling in configuration system 
<https://issues.apache.org/jira/browse/FLUME-1051>
- Flume hot-reconfiguration specification 
<https://issues.apache.org/jira/browse/FLUME-1278>
- OutOfMemory errors in Flume build 
<https://issues.apache.org/jira/browse/FLUME-1256>
- FileChannel hangs silently when Hadoop libs not found 
<https://issues.apache.org/jira/browse/FLUME-1246>




On Wednesday, June 13, 2012 at 12:57 AM, Mike Percy wrote:

> Developers,
> It has been nearly 3 months since we released Flume 1.1.0. Since the 1.1.0 
> release, we have had 117 commits to the trunk, and 114 JIRAs have been marked 
> "Resolved Fixed" with a target of v1.2.0. This flurry of activity represents 
> a whole slew of new features and a bunch of bug fixes.
> 
> Because of the above, I think we should release a Flume 1.2.0 to the world 
> within 2-3 weeks. I propose that I be the release manager for this release. 
> To that end, I would like to cut an SVN branch pretty soon to stabilize and 
> test the code in advance of the release.
> 
> In addition, I'd like to gather input on what other devs would like to see 
> included in a 1.2.0 release.
> 
> Aside from a few JIRAs already marked as Patch Available, the one thing I'd 
> really like to make happen is a once-over on the user guide to cover the 
> latest features. I'm willing to help.
> 
> Regards,
> Mike



Reply via email to