I have had some strange results recently when trying to phase some 
compounds in an AB Integrator 30.

Here are the particulars.

The Integrator is running with a Base Processing Cycle (BPC) of 1 second.

Most of the existing COMPOUNDS are running with a PERIOD 1 PHASE 0.
        (That should be every second, on phase 0)

Most of the BLOCKS in the existing compounds are running with a PERIOD 3 
PHASE 0.
        (That should be every two seconds, on phase 0)

All of this is working correctly.

We added a COMPOUND with a PERIOD 3 PHASE 1.
        (That should be every two seconds, on phase 1)

The BLOCKS in the new compound are PERIOD 3 PHASE 1.
        (That should be every two seconds, on phase 1)

This PERIOD, PHASE combination is acceptable to the control configurator.

However, the ABSCAN block will not successfully connect and read data from 
the PLC at this PERIOD (3) and PHASE (1).  If I change the PHASE to a 0 on 
these COMPOUNDs and BLOCKs every thing works.  But having everything PHASED 
at 0 causes issues with the station loading.

I hope some of you can shed some light on this mystery for me.

Thanks,
David Johnson

[EMAIL PROTECTED]


-----------------------------------------------------------------------
This list is neither sponsored nor endorsed by the Foxboro Company. All 
postings from this list are the work of list subscribers and no warranty 
is made or implied as to the accuracy of any information disseminated 
through this medium. By subscribing to this list you agree to hold the 
list sponsor(s) blameless for any and all mishaps which might occur due to 
your application of information received from this mailing list.

To be removed from this list, send mail to 
[EMAIL PROTECTED] 
with "unsubscribe foxboro" in the Subject. Or, send any mail to
[EMAIL PROTECTED]

Reply via email to