On 18/04/2012 5:00 AM, David Coote wrote:
Whoever first gets a small-scale gasifier up that meets Knoef et al's
proposed criteria on whether or not a gasification technology is
commercial could do very well.
David,

When we decided to build a commercial specification system we set Knoef's criteria as our benchmark. Everything is now capable of being met with those bits pending already in train except the 2000hrs at >80% availability in a contiguous run, and we will possibly be setting up a system to do this when we return from a demonstration event in Victoria at the end of this month (subject to other work loads). This last criteria to be met is more of a material handling issue than a gasifier one, setting up fuel pre-processing in particular, and we now have a chipper and fuel supply to suit. We will start at 10hrs/day (which would still meet the criteria on cumulative operation) but will fit automated feed to run it 24/7 for additional reasons. In any case some of the projects we are involved in will achieve this independently in due course.

This would have been achieved twelve months earlier except for some games played against us by a large public authority on a biosolids and wood chip to biochar and energy project. Having met the first two milestones including independent testing of material blends through the gasifier at Sutton (near Canberra) we built and delivered the complete 200kg/hr working plant for onsite trials only to have the client renege on agreements re siting and attempt to put us in an open, unsecured paddock subject to direct contact with the spray from the treatment pond aerators! Then whilst this was being sorted out they completed the required reports for the State Government funding agency, received the funds for payment of this milestone then withheld these pending us signing new contracts which included granting intellectual property rights to them! We have only just had the court case resulting, and whilst we won the cost has been high and while it was going on resources had to be diverted (and we are still awaiting payment).

So having a working gasifier system is not a guarantee of success.

You are quite right about the numerous "enormous amount of small-scale biomass assets dotted around the countryside" and the 1500tonnes/yr is typical, on a 2500hr/yr duty cycle approximating their normal working days this equates to around 600kg/hr or for arguments sake a nominal 500kWe system. You will find that in practice that this cannot be connected to the grid in the majority of locations where this resource is available, (even at the a nominal 150-200kWe rating if running 24/7) so unless there is a on-site power requirement at this level it is still no go. This is the reality we rudely discovered when we first built a reliable system capable of this scale. In fact even where the grid infrastructure can support it we have found utilities over here extremely reluctant.

The point is benchmarks such as Knoef's in the end have limited value because they assume in the first instance that the barrier to deployment is technical centred only on the gasifier, when in fact it is only when this is overcome that a lot of different and new barriers become apparent. In the end we have found genuine clients seek us out, not the other way round, so achieving some arbitrary benchmark before going commercial is moot.

Innovation in application then does not stop with system design, but rather begins when this is complete!

Peter

_______________________________________________
Gasification mailing list

to Send a Message to the list, use the email address
[email protected]

to UNSUBSCRIBE or Change your List Settings use the web page
http://lists.bioenergylists.org/mailman/listinfo/gasification_lists.bioenergylists.org

for more Gasifiers,  News and Information see our web site:
http://gasifiers.bioenergylists.org/

Reply via email to