Agenda for the meeting today:
- Review open bugs and decide on the release
567     blocker         [EMAIL PROTECTED]       RHEL5 ppc64 UD verbs failures
577 critical [EMAIL PROTECTED] SRP multipath failover too slow (minutes, not seconds) 629 major [EMAIL PROTECTED] ib-bonding: sometimes slow failover is noticed 541 major [EMAIL PROTECTED] slow failover with IPoIB CM bonding/ipoibtools HA 642 major [EMAIL PROTECTED] Failed to build mvapich with PGI compiler



My suggestion wait only for Bonding and MPI fixes and have RC5 done on Wed.
This RC5 should become the official release



In the meeting today we decided the following:
For RC5 we will fix only 2 more issues:
629 - new bonding module is already ready
642 - got approval from OSU so we will enhance MPI to support PGI compiler
558 - Scott should find with Roland if there is a fix for tvflush for SLES10 SP1 and if its fixed we can take this one too.

RC5 will be published on Wed June 13, and it is targeted to become the GA release.
GA release will be published after a week of QA - target date is June 20.

Tziporet

_______________________________________________
general mailing list
[email protected]
http://lists.openfabrics.org/cgi-bin/mailman/listinfo/general

To unsubscribe, please visit http://openib.org/mailman/listinfo/openib-general

Reply via email to