Valve problem hits Kudankulam project
Chennai, Sep 7, 2013 (IANS):

*Problems with valves in the first unit at the Kundankulam Nuclear Power
Project (KNPP) has delayed the synchronisation of the unit with the grid,
officials said.*

The Nuclear Power Corporation of India Ltd (NPCIL), India's atomic power
plant operator, is setting up two 1,000 MW Russian reactors at Kudankulam
in Tirunelveli district, around 650 km from here.

After several years of delay, the first 1,000 MW Russian-made reactor at
KNPP and India's 21st reactor began its nuclear fission process July 13.

The 1,000 MW first unit is expected to be synchronised with the grid in
15-days time, they said.

A senior official of the Atomic Energy Regulatory Board (AERB) told IANS:
"The performance of some parts can be checked only when the power
generation is increased to certain levels."

"While we have issued clearance for the first unit to generate 50 percent
power tests have to be done simultaneously and corrective action are taken."

He said the systems will be checked while increasing the power levels.

"Till the unit gets stabilised at a certain level, power generation will be
increased and decreased," he said.

"Two valves inside the condenser in the first unit seems to have got stuck
and they were later set right.

"NPCIL officials had to go to the root cause of the problem so that it does
not occur again which in turn has taken time," a source told IANS.

The NPCIL started its work at the KNPP's first unit, soon after receiving
AERB's clearance, so as to connect the unit to the grid when it generates
400 MW power.

KNPP site director R.S. Sundar earlier said the first unit would be
connected to the grid by the end of August, generating 500 MW. But that did
not happen perhaps due to the condenser valve problem.

After necessary regulatory clearances, power generation will be increased
gradually to 50 percent, 75 percent, 90 percent and finally 100 percent.

NPCIL officials were not available for comment on the valve problem and the
delay in connecting the first unit of KNPP to the grid.

KNPP is India's first pressurised water reactor belonging to the light
water reactor category.

An industry source said the valves were not in use for a very long time
owing to the project delays and hence they would have caused problems.

"Even in the case of thermal power plants, there will be teething problems
with various components. It will take some time for the plant to stablise.

"The one advantage thermal plant has over nuclear plants is that components
can be changed immediately whereas in the case of the latter, detailed
studies are made and regulatory approvals have to be obtained," an official
of a power plant manufacturing company told IANS

-- 
Peace Is Doable

-- 
You received this message because you are subscribed to the Google Groups 
"Green Youth Movement" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send an email to [email protected].
Visit this group at http://groups.google.com/group/greenyouth.
For more options, visit https://groups.google.com/groups/opt_out.

Reply via email to