June,

It is my understanding that testing has already started. The label is just a 
label, but we have had misunderstandings in the past, so I want to make sure.

Erich,

Please tag the release using the upper case form. Please use an annotated tag 
and an appropriate comment.

Pat

From: ???(June Yong Young) [mailto:[email protected]]
Sent: Wednesday, May 27, 2015 3:43 AM
To: Lankswert, Patrick; Agrawal, Sachin; iotivity-dev at lists.iotivity.org; 
'???'; '???'
Subject: RE: [dev] 0.9.1 release schedule

Hi Pat, Thiago,

Is there any problme in freezing the code? Would you please let us know?
We have no time. We should have 3 days for QA to finalize the test before 
official release.

Regards
June

June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair
IoTivity Release Function Lead

Samsung Electronics Co.,Ltd.
Software R&D Center, IoT Solution Lab. | Web & Convergence Team
Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107
E-mail :juney at samsung.com

From: ???(June Yong Young) [mailto:[email protected]]
Sent: Wednesday, May 27, 2015 1:48 PM
To: 'Lankswert, Patrick'; 'Agrawal, Sachin'; 'iotivity-dev at 
lists.iotivity.org'; '???'; '???'
Subject: RE: [dev] 0.9.1 release schedule

Hi Pat,

What is your progress on 0.9.1-RC1 release?

Regards
June

June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair
IoTivity Release Function Lead

Samsung Electronics Co.,Ltd.
Software R&D Center, IoT Solution Lab. | Web & Convergence Team
Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107
E-mail :juney at samsung.com

From: ???(June Yong Young) [mailto:[email protected]]
Sent: Wednesday, May 27, 2015 10:08 AM
To: 'Lankswert, Patrick'; 'Agrawal, Sachin'; 'iotivity-dev at 
lists.iotivity.org'; '???'; '???'
Subject: RE: [dev] 0.9.1 release schedule

Hi Pat,

?0.9.1-RC1? capital case is right.
When 0.9.0 was released, it was ?0.9.0-RC1?

BTW, RC1 has not been tagged yet. When do you expect it will be made?

Regards,
June

June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair
IoTivity Release Function Lead

Samsung Electronics Co.,Ltd.
Software R&D Center, IoT Solution Lab. | Web & Convergence Team
Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107
E-mail :juney at samsung.com

From: Lankswert, Patrick [mailto:[email protected]]
Sent: Tuesday, May 26, 2015 10:57 PM
To: juney at samsung.com<mailto:juney at samsung.com>; Agrawal, Sachin; 
iotivity-dev at lists.iotivity.org<mailto:iotivity-dev at lists.iotivity.org>; 
'???'; '???'
Subject: RE: [dev] 0.9.1 release schedule

June,

Sure. Just to be sure, aren?t we using lower case tags now? So should it be 
?0.9.1-rc1??

Pat

From: ???(June Yong Young) [mailto:[email protected]]
Sent: Tuesday, May 26, 2015 7:04 AM
To: Lankswert, Patrick; Agrawal, Sachin; iotivity-dev at 
lists.iotivity.org<mailto:iotivity-dev at lists.iotivity.org>; '???'; '???'
Subject: RE: [dev] 0.9.1 release schedule

Hi Pat,

What is your progress?
Uze has finalized Samsung code now, so you can tag ?0.9.1-RC1? now if Intel 
code is finalized.

Regards,
June

June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair
IoTivity Release Function Lead

Samsung Electronics Co.,Ltd.
Software R&D Center, IoT Solution Lab. | Web & Convergence Team
Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107
E-mail :juney at samsung.com


From: JuneYong Young [mailto:[email protected]]
Sent: Monday, May 18, 2015 2:21 AM
To: ???; Agrawal, Sachin; Lankswert, Patrick; iotivity-dev at 
lists.iotivity.org<mailto:iotivity-dev at lists.iotivity.org>; ???; ???
Subject: Re: [dev] 0.9.1 release schedule


To all,



I've slightly revised some items below after discussion with Samsung QA.


- 0.9.1 : ?Spec vA Mandatory features?

- Schedule

  . 5/20, Feature complete & Review Complete and make "0.9.1-RC1" release to QA

  . 5/25, QA reports back.

  . 5/26, "0.9.2-RC2" release just in case there an issue occurs on basic 
functionality

  . 5/28, QA to run Sanity check (about only the issue items)

  . 5/29, Website Open

- Mandatory items must be completed

  . Any basic functionality should be working

  . Merge CA(connectivity Abstraction) branch onto one master branch

- The items strongly requested, but no gating issues to release

  . BT/BLE Support, Noti. Manager, Android API

  . If any issues related to these items, they will be described as known 
issues.

- QA

  . P1 problems to be fixed.

 If it is not fixed, then it has to be lowered down to P2 after discussion with 
QA.



To Pat,

George is a release manangement function counter part of Intel side.

Please check with Intel QA since George is not present now.





Regards

June


June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair
IoTivity Release Function Lead

Samsung Electronics Co.,Ltd.
Software R&D Center,  IoT Solution Lab. | Web & Convergence Team
Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107
E-mail :juney at samsung.com



------- Original Message -------

Sender : ???<juney at samsung.com<mailto:juney at samsung.com>> S6(??)/??/IoT 
Solution Lab(S/W??)/????

Date : 2015-05-15 11:40 (GMT+09:00)

Title : [dev] 0.9.1 release schedule


To all,

According to the discussion result in the last ISG & OSWG F2F meeting,
we will release & open 0.9.1 at the end of May with schedule driven.

So, 0.9.1 will be released based on the following. If any questions or 
concerns, then let us know.

- 0.9.1 : ?Spec vA Mandatory features?

- Schedule

 . 5/22, Feature complete & Review Complete

 . 5/28, exit from QA

 . 5/29, Website Open

- Mandatory items must be completed

 . Merge CA(connectivity Abstraction) branch onto one master branch

- The items strongly requested, but no gating issues to release

 . BT/BLE Support, Noti. Manager, Android API

- QA

 . P1 problems to be fixed.

If it is not fixed, then it has to be lowered down to P2 after discussion with 
QA.

[cid:image001.png at 01D09872.091E51A0]

June Yong Young
OIC Open Sourece WG Project Planning & Requirement TG Chair
IoTivity Release Function Lead

Samsung Electronics Co.,Ltd.
Software R&D Center, IoT Solution Lab. | Web & Convergence Team
Principal Engineer

T: +82-31-301-6107, M: +82-10-9530-6107
E-mail :juney at samsung.com

From: iotivity-dev-bounces at lists.iotivity.org<mailto:iotivity-dev-bounces at 
lists.iotivity.org> [mailto:[email protected]] On Behalf 
Of Agrawal, Sachin
Sent: Friday, May 15, 2015 8:30 AM
To: Lankswert, Patrick; iotivity-dev at lists.iotivity.org<mailto:iotivity-dev 
at lists.iotivity.org>
Subject: Re: [dev] Last call for contributions for 0.9.1

Hi Pat,

Can you clarify this statement?
?Failing to do so will result in your contribution being held until the next 
release?

My assumption is that ?master? will still be open for code check-ins, except 
that the check-in?s
after May 28th will NOT be tagged for 0.9.1 release.
Is that right?

Thanks
Sachin
503-264-8071

From: iotivity-dev-bounces at lists.iotivity.org<mailto:iotivity-dev-bounces at 
lists.iotivity.org> [mailto:[email protected]] On Behalf 
Of Lankswert, Patrick
Sent: Wednesday, May 13, 2015 2:21 PM
To: iotivity-dev at lists.iotivity.org<mailto:iotivity-dev at 
lists.iotivity.org>
Subject: [dev] Last call for contributions for 0.9.1

To all,

The following dates are important for the 0.9.1 release:
June 5th ? Code Freeze
May 28th ? Feature Complete and Review Complete

It is important that contributions be completed by May 28th, so that system 
testing may start.

If you have a contribution that you want considered for 0.9.1 that is not 
already in gerrit review, you must announce on this list with an estimated date 
for your submission. Failing to do so will result in your contribution being 
held until the next release.

We are working on a more formal release schedule process what will be published 
on the wiki.

Pat

Patrick Lankswert
Discovery and Connectivity (Core Stack) Maintainer

[cid:image002.gif at 01D09872.091E51A0]

[http://ext.samsung.net/mailcheck/SeenTimeChecker?do=c7ba9f2f7185d6393c28b3c940eb11c25a9f8d8a74e3363d87dfe03c47d8dbcb08c5ce1bd480a15cd4a87a1fb2ad96504bea3c1765014a1208cece8541bc14eacf878f9a26ce15a0]
-------------- next part --------------
An HTML attachment was scrubbed...
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150527/ac0f940c/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 141688 bytes
Desc: image001.png
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150527/ac0f940c/attachment.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.gif
Type: image/gif
Size: 13168 bytes
Desc: image002.gif
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20150527/ac0f940c/attachment.gif>

Reply via email to