These are new feature list beyond existing feature from 1.2.x.
Let me check the progress of each item from percentage view.
Please answer the progress of each item from implementation and test
perspective respectively.
Because there are lots of items in the release, Let me remove the feature with
no responding in spite of requests.
* Example to answer. Introspection -implementation: 100%, TC is made by
IoTivity QA and 70% progress.
Introspection code merged into master.
any remaining fix item? Implement progress from percentage view?
Test is agreed with IoTivity QA lead? And progress for TC implementation from
percentage view?
Versioning code merged into master.
any remaining fix item? Implement progress from percentage view?
Test is agreed with IoTivity QA lead? And progress for TC implementation from
percentage view?
Endpoint code merged into master.
any remaining fix item? Implement progress from percentage view?
Test is agreed with IoTivity QA lead? And progress for TC implementation from
percentage view?
Security update Feature is not merged yet, already we are communicating it.
Let me tracking.
MPM expected scope is merged into master?
[Todd] Yes
any remaining fix item?
[Todd] None known except IOT-1964.
Implement progress from percentage view?
[Todd] 100%
Test is agreed with IoTivity QA lead? And progress for TC implementation from
percentage view?
[Todd] Unit tests are being developed, discussing with Antu.
AllJoyn Bridge expected scope is merged into master?
[Todd] iotivity.git: Yes
iotivity-alljoyn-bridge.git: No
any remaining fix item?
[Todd] iotivity.git: IOT-1935, IOT-1940, IOT-1941, IOT-1942
Implement progress from percentage view?
[Todd] iotivity.git: With the exception of the above, 100%
iotivity-alljoyn-bridge.git: 75%, introspection in progress and
need to update to latest rev of bridging spec
Test is agreed with IoTivity QA lead? And progress for TC implementation from
percentage view?
[Todd] iotivity.git: unit tests are in place, discussing with Antu.
iotivity-alljoyn-bridge.git: discussing with Antu.
UPnP Bridge Updates expected scope is merged into master?
any remaining fix item? Implement progress from percentage view?
Test is agreed with IoTivity QA lead? And progress for TC implementation from
percentage view?
WiFi Easy-Setup update resource model update has been merged into master
branch.
Test is agreed with IoTivity QA lead? And progress for TC
implementation from percentage view?
CoAP Native Cloud project (Resource Model Update, Web Socket)
expected scope is merged into master?
any remaining fix item? Implement progress from percentage view?
Test is agreed with IoTivity QA lead? And progress for TC implementation from
percentage view?
Generic Java Binding expected scope is merged into master?
Test is agreed with IoTivity QA lead? And progress for TC implementation from
percentage view?
BR, Uze Choi (IoTivity Release Function Lead)
-------------- next part --------------
An HTML attachment was scrubbed...
URL:
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20170405/69d6254a/attachment.html>