Hi Nathan,


I don't think pushing this out one week will impact PF #12 too much.
Vendors will still have one week to integrate v1.3 if they choose.



I would rather have as many security CRs implemented in v1.3 than trying to
rush and miss out on some key features.  As Nathan said, so many of the
security CRs are related to and dependent on each other.  Trying to pull out
one or two of the CRs that Nathan is working on will potentially make the
whole thing fall apart.  Putting it back together will most likely require
normative spec changes that should be avoided when possible.



This is not my decision but I don't think Nathan's request sounds
unreasonable.



Mitch



From: Heldt-Sheller, Nathan [mailto:[email protected]] 
Sent: Thursday, March 30, 2017 4:51 PM
To: iotivity-dev at lists.iotivity.org; oswg at openconnectivity.org;
security_os_tg at openconnectivity.org
Cc: ???(Uze Choi) (uzchoi at samsung.com); Mitch Kettrick; ??? ?? OCF Sec
Subject: Request to postpone IoTivity 1.3-rel branch date from April 7th to
April 17th



Hello OSWG, IoTivity-dev and OSWG Security TG,



As many of you know, being a volunteer project, we've been short-handed on
developers, and struggling to find resources for several Security features.
I've been asking for months for additional help with a few features, but
being unable to find volunteers, I have picked up implementation of these
myself.



However just after returning from the Amsterdam F2F, I learned that one of
our key development resources was moving on to another job.  I'm not able to
pick up this slack, since I'm already overloaded.   And because of the
inter-dependent nature of these features, although myself and others have
tried, it has been infeasible to cut out any additional CRs from the
Security Spec. to do so would be more work than just implementing what we
have (not to mention significant normative CRs).



The good news is that just today I've gotten some temporary resource
commitment from inside Intel, to pick up these newly-ownerless tasks.
However I think because of the time lost over the past few weeks, and
spin-up required, it would greatly increase our odds of success to have
another week of development time before creating the 1.3-rel branch.
Moreover, at the last OSWG Security TG meeting, I believe Dongik Lee
mentioned that their team would like a little more time (if possible) to
implement a couple additional items they're working on.


TLDR; if there is not a hard-stop reason why we need to branch next Friday
April 7th, I propose we take an additional work-week (plus the weekend for
those of us who need to work through it) and create the 1.3-rel branch on
Monday April 17th.



Uze, I think the decision is yours ultimately, but I'm sending to the entire
list to gather feedback in case there are folks counting on this April 7th
date for a reason we're not aware of.



Thanks,
Nathan Heldt-Sheller

OSWG Security TG Chair





---
This email has been checked for viruses by AVG.
http://www.avg.com
-------------- next part --------------
An HTML attachment was scrubbed...
URL: 
<http://lists.iotivity.org/pipermail/iotivity-dev/attachments/20170330/049f4e67/attachment.html>

Reply via email to