[ 
https://issues.apache.org/jira/browse/AMBARI-15637?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
 ]

Alejandro Fernandez updated AMBARI-15637:
-----------------------------------------
    Attachment:     (was: AMBARI-15637.branch-2.2.patch)

> If RU/EU is paused, services are restarted on the older version. EU is more 
> complex since stopping services should use the original version.
> --------------------------------------------------------------------------------------------------------------------------------------------
>
>                 Key: AMBARI-15637
>                 URL: https://issues.apache.org/jira/browse/AMBARI-15637
>             Project: Ambari
>          Issue Type: Bug
>          Components: ambari-server
>    Affects Versions: 2.2.2
>            Reporter: Alejandro Fernandez
>            Priority: Critical
>             Fix For: 2.2.2
>
>
> Currently, if RU/EU is paused, then restarting services manually will use the 
> version whose state is CURRENT. This means that services may be restarted on 
> the wrong version, preventing Ambari from correctly Finalizing the upgrade.
> Instead, the logic should be as follows during Upgrade:
> RU: always use to_version
> EU: if haven't completed the action "UPDATE_DESIRED_STACK_ID", then use the 
> from_version, otherwise, use the to_version.
> During Downgrade, both should use the original version, which is actually the 
> to_version column in the upgrade table.
> Assertions:
> A: restart a service (should have version parameter,
> B: run a service check (no version needed)
> C: run HDFS Rebalance (should have version parameter).
> Test Cases:
> 1. Before stack upgrade, run A, B, and C, which should all use the current 
> version
> 2. EU, immediately click pause. Run A, B, and C, which should use the 
> original version if it exists
> 3. EU, after the services have been stopped and the stack has been upgraded. 
> Run A, B, and C, which should use the new version since the services are now 
> to be started.
> 4. EU, click downgrade and pause. Run A, B, C, which should use the original 
> version.
> 5. RU, click pause whenever a manual task occurs. Run A, B, and C, which 
> should use the destination version.
> 6. RU, click downgrade. Run A, B, and C, which should use the original 
> version.



--
This message was sent by Atlassian JIRA
(v6.3.4#6332)

Reply via email to