Zhu Zhu created FLINK-17726: ------------------------------- Summary: Scheduler should take care of tasks directly canceled by TaskManager Key: FLINK-17726 URL: https://issues.apache.org/jira/browse/FLINK-17726 Project: Flink Issue Type: Bug Components: Runtime / Coordination Affects Versions: 1.12.0 Reporter: Zhu Zhu Fix For: 1.12.0
JobManager will not trigger failure handling when receiving CANCELED task update. This is because CANCELED tasks are usually caused by another FAILED task. These CANCELED tasks will be restarted by the failover process triggered FAILED task. However, if a task is directly CANCELED by TaskManager due to its own runtime issue, the task will not be recovered by JM and thus the job would hang. This is a potential issue and we should avoid it. A possible solution is to let JobManager treat tasks transitioning to CANCELED from all states except from CANCELING as failed tasks. -- This message was sent by Atlassian Jira (v8.3.4#803005)