https://issues.apache.org/jira/browse/HBASE-14614?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=15974088#comment-15974088
 ] 

stack commented on HBASE-14614:
-------------------------------

Just an update. I've been working this patch on cluster. Interesting bugs. 
Keeping account up in 
https://docs.google.com/document/d/1eVKa7FHdeoJ1-9o8yZcOTAQbv0u0bblBlCCzVSIn69g/edit#
 See BUGs section. Two bad ones. 1. when subprocedures are done, they fail 
because their parent finished early (miscounting -- two worker threads can run 
same procedure...), and 2. after crash, for some reason, we do not reschedule 
an odd proc.. trying to figure it. There are others and have been working on 
log cleanup so has narrative; i.e. always log procId along side event change so 
can associate procedure and log message... etc. Will be back w/ more status. 
See doc in meantime if you would like to follow along.

> Procedure v2: Core Assignment Manager
> -------------------------------------
>
>                 Key: HBASE-14614
>                 URL: https://issues.apache.org/jira/browse/HBASE-14614
>             Project: HBase
>          Issue Type: Sub-task
>          Components: proc-v2
>    Affects Versions: 2.0.0
>            Reporter: Stephen Yuan Jiang
>            Assignee: Matteo Bertozzi
>             Fix For: 2.0.0
>
>         Attachments: HBASE-14614.master.003.patch, 
> HBASE-14614.master.004.patch, HBASE-14614.master.005.patch, 
> HBASE-14614.master.006.patch, HBASE-14614.master.007.patch, 
> HBASE-14614.master.008.patch, HBASE-14614.master.009.patch, 
> HBASE-14614.master.010.patch, HBASE-14614.master.011.patch, 
> HBASE-14614.master.012.patch, HBASE-14614.master.012.patch, 
> HBASE-14614.master.013.patch, HBASE-14614.master.014.patch, 
> HBASE-14614.master.015.patch, HBASE-14614.master.017.patch, 
> HBASE-14614.master.018.patch, HBASE-14614.master.019.patch, 
> HBASE-14614.master.020.patch, HBASE-14614.master.021.patch, 
> HBASE-14614.master.022.patch, HBASE-14614.master.023.patch, 
> HBASE-14614.master.024.patch, HBASE-14614.master.025.patch, 
> HBASE-14614.master.026.patch, HBASE-14614.master.027.patch, 
> HBASE-14614.master.028.patch, HBASE-14614.master.029.patch, 
> HBASE-14614.master.030.patch, HBASE-14614.master.031.patch, 
> HBASE-14614.master.032.patch, HBASE-14614.master.033.patch, 
> HBASE-14614.master.034.patch, HBASE-14614.master.035.patch, 
> HBASE-14614.master.036.patch, HBASE-14614.master.037.patch, 
> HBASE-14614.master.038.patch
>
>
> New AssignmentManager implemented using proc-v2.
>  - AssignProcedure handle assignment operation
>  - UnassignProcedure handle unassign operation
>  - MoveRegionProcedure handle move/balance operation
> Concurrent Assign operations are batched together and sent to the balancer
> Concurrent Assign and Unassign operation ready to be sent to the RS are 
> batched together
> This patch is an intermediate state where we add the new AM as 
> AssignmentManager2() to the master, to be reached by tests. but the new AM 
> will not be integrated with the rest of the system. Only new am unit-tests 
> will exercise the new assigment manager. The integration with the master code 
> is part of HBASE-14616



--