https://issues.apache.org/jira/browse/HIVE-12013?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
 ]

Sergey Shelukhin updated HIVE-12013:
------------------------------------
    Description: 
Tests cannot be parallelized before we merge, and tests cannot run fast enough 
(they did once, so I guess cannot always run fast enough) when they are not 
parallelized, and we need tests to pass before merging.
LLAP is off by default, we did see tests pass recently (with the exception of a 
few out file diffs), and some tests will still be run, so it should be ok to 
proceed as follows.
We will disable most of the LLAP q tests for now, merge, enable paralllelism 
and re-enable.

  was:
Tests cannot be parallelized before we merge, and tests cannot run fast enough 
(they did once, so I guess cannot always run fast enough) when they are not 
parallelized.
LLAP is off by default, we did see tests pass recently (with the exception of a 
few out file diffs), and some tests will still be run, so it should be ok to 
proceed as follows.
We will disable most of the LLAP q tests for now, merge, enable paralllelism 
and re-enable.


> LLAP: disable most llap tests before merge
> ------------------------------------------
>
>                 Key: HIVE-12013
>                 URL: https://issues.apache.org/jira/browse/HIVE-12013
>             Project: Hive
>          Issue Type: Bug
>            Reporter: Sergey Shelukhin
>
> Tests cannot be parallelized before we merge, and tests cannot run fast 
> enough (they did once, so I guess cannot always run fast enough) when they 
> are not parallelized, and we need tests to pass before merging.
> LLAP is off by default, we did see tests pass recently (with the exception of 
> a few out file diffs), and some tests will still be run, so it should be ok 
> to proceed as follows.
> We will disable most of the LLAP q tests for now, merge, enable paralllelism 
> and re-enable.



--
This message was sent by Atlassian JIRA
(v6.3.4#6332)

Reply via email to