While the issue relating to the clause, capping number of highway projects a 
company can bid for and finally execute, still hinges on the Delhi High Court's 
verdict, two mega highways projects have seen withdrawal of all shortlisted 
bidders at the financial bidding stage. Also, a large number of big-ticket 
projects have seen withdrawals by highways construction majors due to the 
clause. 

The two stretches that have seen withdrawal by all six bidders each at the 
financial bidding stage are, 121 km Vijaywada-Machilipatnam and 71-km 
Kundapur-Surathkal. 

The bidders have withdrawn quoting the additional eligibility clause introduced 
by the ministry of road transport and highways in August this year. 

The ministry in a letter to NHAI on the issue said, "A bidder shall not be 
eligible for bidding if the bidder, its member or associate, was during a 
period of two months preceding the bid due date, either by itself or as a 
member of consortium prequalified for bid stage in eight or more projects or 
declared as selected bidder for four projects." 

This is applicable on all the 53 projects, which the NHAI put on block in 
September this year. 

As a fallout, shortlisted bidders started withdrawing from projects, rendering 
the two stretches with no takers. A top NHAI official, however, said, "In case 
of the two projects where all the bidders have withdrawn, rebidding will be 
done." 

The two projects are a part of Lot I of national highways development 
programme, phase III. There are 23 projects in the lot worth around Rs 30,000 
crore. More than half of the projects have seen withdrawals by highway builders 
at the financial bidding stage. The bidding for all the 44 projects under phase 
III is scheduled to be over by December this year. However, had the National 
Highways Authority of India (NHAI) followed its schedule for financial bidding, 
it would have wrapped up the process for at least ten projects of Lot I by now. 

Incidentally, construction major Larsen and Toubro, which was short-listed for 
financial bidding of 15 projects withdrew from eight. Reliance Infrastructure, 
which had been shorlisted for 13 projects, has withdrawn from nine projects. 
Similarly, GMR Infrastructure has withdrawn from six projects. 

Speaking on the withdrawals by the companies quoting the clause, Gajendra 
Haldea, principal advisor (infrastructure), Planning Commission, said, "There 
is nothing wrong in the regulation. The regulation has been imposed to avoid 
monopoly situation. As far as the projects that have seen withdrawals by all 
the bidders are concerned, NHAI will take due action in that case." 

However, M Murali, director general of National Highways Builders Federation, a 
representative body of highways builders said, "Suppose a company's capacity 
allows it to take up more projects, why should it be compelled from bidding. 
Restricting people from bidding and participating in a project will result in 
under utilizing the capacity. Also, this is against the Competition Law." 

The clause imposing the caps on the number of projects a bidder can take up has 
been challenged in the court. However, taking cue from the court's decision on 
another clause capping number of bidders at financial bidding stage at top 
five/six, it is unlikely that the bidders will get any reprieve in this case as 
well. 

The Delhi High Court in its judgment on Monday said, "The government has the 
right to implement, amend any rules and regulations on the policy matter, which 
may be implemented from time to time. 

Since it is a government policy decision to exempt the deletion of clause 3.5.2 
(cap on number of bidders for financial bidding) in model concession agreement 
in 60 projects, the Court feels they should not interfere in policy decisions

http://www.financialexpress.com/news/bidding-cap-leaves-few-takers-for-nhai-projects/381547/
"All you need is ignorance and confidence; then success is sure."









--~--~---------~--~----~------------~-------~--~----~
You received this message because you are subscribed to the Google Groups 
"Kences1" group.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to [EMAIL PROTECTED]
For more options, visit this group at 
http://groups.google.com/group/kences1?hl=en
-~----------~----~----~----~------~----~------~--~---

Reply via email to