Hi,

V ?t, 21. 07. 2009 v 15:22, Milan Jurik p??e:
> Hi Irek,
> 
> status:
> 
> 1) Test plan and Checklist approved for C-team inception review
> 2) ON C-team inception review on Monday 27th July

Inception review passed, few minor nits I need to cleanup in the
Checklist.

> 3) Performance testing on-going still

I am still waiting for the results

> 4) final VSC testing in progress, with good results for now

SPARC 32/64-bit UNIX98 and UNIX03 testing passed, x86 in progress. Many
thanks to Pradhap for this.

> 5) OpenSolaris distro related testing done
> 6) ON/Net PIT testing done
> 7) Live-upgrade testing not done yet because of RE was busy, it should
> be done this week

In progress yet.

> 8) On-going evaluation how to integrate ksh93 regression testing
> 

Only waits for me to fill the request now.

> I will know more after Monday's meeting. I am sorry it takes so much
> time, but we cannot have similar problems like last time once again and
> from all delays Roland was able to create bugfixes for new discovered
> problems.
> 

2 weeks of not busy QA and we can go to final review and putback if
there will be no stopper.

As for new phase with submitted and "withdrawn" ARC case I do not know,
because it is unlikely I will be sponsoring the next phases, somebody
else will be needed.

Best regards,

Milan


Reply via email to