We are getting close to the end of the month and in theory we should
enter freeze around next week if we want to release 1.2.11 early Dec.
However:
  - we have 'only' 150 commits since 1.2.10
  - December is usually heavilly truncated due to Xmas/etc... vacations
  - I'm actually on vacations next week and while I could try to push
    the release candidates while on the road it's not ideal

What about pushing the 1.2.11 release to around 15th December (maybe a
bit earlier) then push the following release to the last week of
January, just before FOSDEM so it's available then, and also because Feb
is really short.

  Opinions ? I'm tempted to do that '2 release in 3 months' trick, we
did that in the past for end of year,

   Any objections ?

    thanks,

Daniel

-- 
Daniel Veillard      | Open Source and Standards, Red Hat
veill...@redhat.com  | libxml Gnome XML XSLT toolkit  http://xmlsoft.org/
http://veillard.com/ | virtualization library  http://libvirt.org/

--
libvir-list mailing list
libvir-list@redhat.com
https://www.redhat.com/mailman/listinfo/libvir-list

Reply via email to