The Infrastructure team weekly report for 2011-03-10 is now available
and can be found at:

  https://wiki.linaro.org/Platform/Infrastructure/Status/2011-03-10

The report is also reproduced in full below.

Regards,
Jamie.
--
Linaro Release Manager   |   Platform Project Manager

--
 * Period: (20110303-20110309)
 * PM: JamieBennett <jamie.benn...@linaro.org>
 * Past reports : https://wiki.linaro.org/Platform/Infrastructure/Status
 * Burndown information :
    http://status.linaro.org/linaro-infrastructure.html
 * Stakeholder process:
    https://wiki.linaro.org/Platform/Infrastructure/CurrentProjects

== Key Points for wider discussion ==
 * A 'feature-complete' version of the Android build system front-end to
   Jenkins is available at {{{https://android-build.linaro.org/mockup/}}}.
   Builds can be done by members of the ~linaro-android-builders Launchpad
   team and the actual Jenkins instance can be found at
   {{{http://android-build.linaro.org/jenkins}}}. Please take a look and
   give comments.
 * svammel mass bug filing tool for build failures is progressing. Some
   more improvements planned but initial reviews are favorable. Code
   reviews are welcome.
  
== Team Highlights ==
 * ec2 investigations continue to find the best solution for the
   continuous integration service. An ebs instance either small or large
   for the master and include slaves as when needed for builds seems the
   most effective.
 * Mattias and Deepti now have Panda boards although Deepti's is shared
   at the moment.
 * Initial patch tracking metrics have been given to management.
 * Tracking bugs as work items on non-Ubuntu projects was enabled in the
   status.linaro.org code.
 * Initial work on a planet instance for Linaro has been undertaken. The
   results can be found at
   [[http://ec2-50-17-53-200.compute-1.amazonaws.com/]]

== Upcoming Deliverables ==
 * linaro-image-tools will be getting a release soon (likely before the
   monthly release date to ease the process of getting it in to Ubuntu)
 * Final patch metrics for the next member report in two weeks.

== Risks / Issues ==
 * '''VERY HIGH IMPACT''': Mattias unable to work productively due to IT
   restrictions in ST-E (5 weeks): some progress. Has process now to
   request changes, but little response to his requests in more than 4
   weeks. Mattias is working from home or over 3G in the meantime.
 * '''HIGH IMPACT''': PatchTracking requires deploying Patchwork (4
   weeks): Discussion with IS, and it is not expected to take them long to
   do once they get to it. They have indicated that they may be able to
   start at the end of this week, or in the week after.
 * '''HIGH IMPACT''': Gerrit instance needed for Android (4 weeks):
   Co-ordination with IS has started. Waiting to hear from them if we can
   get it this month, and what we need to do to help with that.
 * '''HIGH IMPACT''': Deepti believes she has not been granted travel to
   Linaro@UDS (2 weeks): She will attend remotely where possible.
 * '''HIGH IMPACT''': A large portion of James' time is taken by project
   management at the moment (several weeks): investigations are in progress
   on how to move most of this work onto a PM.
 * '''MEDIUM IMPACT''': Deepti lacking hardware to work with her Panda
   board: Deepti has received the Panda board, but doesn't have a
   USB->serial cable for it, so is still unable to use it for much. Working
   on tasks that don't require it, but unable to participate in image
   testing. (many weeks).
 * '''MEDIUM IMPACT''': OurOwnOffspring lacking hardware (many weeks):
   x86 for master is ready and waiting, XMs for slaves delivered to IS.
   Awaiting setup from IS.
 * '''MEDIUM IMPACT''': Want a Jenkins/Hudson instance for Continuous
   Integration purposes (many weeks): Discussions with IS, and they will
   provide one, but timeframe is unclear at this point. Will host ourselves
   until IS can provide. Work on getting an ec2 instance for this has
   started, and we should have it running in ec2 by next week.
 * '''MEDIUM IMPACT''': Deepti and Avik are sharing one Panda board
   meaning some hardware specific work is being blocked (1 week).

== Miscellaneous ==
 * Guilherme at PyCon 10-15 March
 * James away 21st March
 * Deepti on vacation 11th March

_______________________________________________