Correct, I run the second.

lsc -s job1
lsc -s job2
.. etc each with whatever clean options I want. My password and user jobs
are separate, so I want to be sure the user stuff is done before password
stuff.

-Joel


On Wed, Apr 17, 2013 at 2:19 AM, [email protected] <[email protected]>wrote:

> Hi Joel,
>
> You run this command:
>
> # lsc --synchronize task1,task2,task3
>
>
> or these commands:
>
> # lsc --synchronize task1
>
> # lsc --synchronize task2
>
> # lsc --synchronize task3
>
>
> thanks
>
> max
>
>
>
>
>
>  ----Messaggio originale----
> Da: [email protected]
> Data: 16-apr-2013 19.51
> A: "[email protected]"<[email protected]>, "lsc-userslsc-users"<
> [email protected]>
> Ogg: Re: [lsc-users] Set priority for task
>
>
> I accomplish this by calling each task specifically in the order I want
> them ran, rather then doing all.
>
> -Joel
>
> On Tuesday, April 16, 2013, [email protected] wrote:
>
>> Hi, my lsc.xml provides 3 tasks. The order of the task is important
>> because
>> task 2 shall be executed after task 1 and task 3 must be executed after
>> task 2.
>> The problem is that task 2 is executed before the task 1.
>> How can I force the order of execution?
>> thanks
>> Sincerely
>> max
>> _______________________________________________________________
>> Ldap Synchronization Connector (LSC) - http://lsc-project.org
>>
>> lsc-users mailing list
>> [email protected]
>> http://lists.lsc-project.org/listinfo/lsc-users
>>
>
>
>
>
_______________________________________________________________
Ldap Synchronization Connector (LSC) - http://lsc-project.org

lsc-users mailing list
[email protected]
http://lists.lsc-project.org/listinfo/lsc-users

Reply via email to