Yup...transfer switches, etc are going to be VERY important and my current thought is to utilize the science logic scripting system to force certain things to happen in a particular order...like wait time for generator to stabilize instead of instant switch over.
/brian chee On 11/8/10 1:45 PM, "John Call" <johnc...@byuh.edu> wrote: > Are you factoring in for the auto-transfer switch and electrical contact work > as well? I'm doing an 80kW presently... > > John > > Sent from my Samsung Epic™ 4G > > Brian Chee <c...@hawaii.edu> wrote: > > > So I¹m looking at exploring the potential for a small (approx 20kw) > generator to get past long (more than 20 minutes) power outages for critical > servers. Does anyone have some wisdom they can share with me? > > /brian chee > > -- > Brian Chee > University of Hawai'i at Manoa > School of Ocean and Earth Sciences and Technology (SOEST) > 2525 Correa Road, HIG 500 > Honolulu, HI 96822 > Tel: 808-956-5797 > > > _______________________________________________ > LUAU@lists.freesoftwarehawaii.org mailing list > http://lists.freesoftwarehawaii.org/listinfo.cgi/luau-freesoftwarehawaii.org > _______________________________________________ > LUAU@lists.freesoftwarehawaii.org mailing list > http://lists.freesoftwarehawaii.org/listinfo.cgi/luau-freesoftwarehawaii.org -- Brian Chee University of Hawai'i at Manoa School of Ocean and Earth Sciences and Technology (SOEST) 2525 Correa Road, HIG 500 Honolulu, HI 96822 Tel: 808-956-5797 _______________________________________________ LUAU@lists.freesoftwarehawaii.org mailing list http://lists.freesoftwarehawaii.org/listinfo.cgi/luau-freesoftwarehawaii.org