As Dr. Zimmerman has said at least one generator is required at slack bus to 
run load flow, one can assume the substation bus where power is incoming as 
slack bus and place an equivelent generator at that bus to run distribution 
load flow.



Best of Luck.    



Kanwardeep Singh



On Tue, 06 Oct 2009 21:45:28 +0530  wrote

>You will need at least a single generator at the slack bus.

--Ray ZimmermanSenior Research Associate211 Warren Hall, Cornell University, 
Ithaca, NY 14853phone: (607) 255-9645



On Oct 6, 2009, at 1:54 AM, Kanishk Chaudhary wrote:On Tue, Oct 6, 2009 at 
11:11 AM, Neeraj Gupta  wrote:

ok



tell me what level of knowledge you have.





Kanishk Chaudhary

> sir,

>   please guid me regarding how to run radial distribution load flow by

> mat

> power.

>

> Kanishk Chaudhary

> BTech electrical final student

> IET lucknow(indian)

>





--

*************************

Neeraj Gupta

Research Scholar, P&C(EE)

Y6104097

IIT Kanpur

************************



Sir,i m final year EE student doing project on capacitor placement on radial 
distribution system. i m tying to run load flow on matpower on default newton 
PF. I took data from Baran n wu reconfiguration 32 us data ......there is 
problem while running the load flow as data priscibe as in case9 is not same 
what i put for 32bus data....as what i take bus one as slake bus remaining PQ 
bus .....the runpf is having error because there is no generator data in what i 
enter there is only BUS AND LINE data....so please sir help to this problem.

Kanishk Btech 4th year EE studentIET lucknow  



Reply via email to