thanku so much sir...
i need one more help, which command can be used for CPF IN IEEE 14 BUS TEST 
SYSTEM so as to obtain real power flow after each corrector predictor step in 
the graph.  


    On Thursday, 26 November 2015 2:03 AM, Ray Zimmerman <r...@cornell.edu> 
wrote:
 

 I don’t think there is anything special about the number of buses. These are 
just systems whose data has been published and then used by many researchers.
   Ray


On Nov 24, 2015, at 6:22 PM, Yogess H Singh <yosh....@gmail.com> wrote:
Dear all,
I am wondering if someone can explain the reason behind choosing the certain 
number of buses such as 9 bus, 14 bus, 39 bus and so on for the standard test 
systems?I know these systems represent some portions of existing power grid 
networks for example IEEE-14 Bus system is a portion of American Electric Power 
System (in the Midwestern US) as of February, 1962.
But other than this is there any other reason of standardization of the test 
systems?

Best Regards,
Yogesh KumarGraduate Research AssistantNE 2042, EECS DepartmentUniversity of 
Toledo, OH 43507+1 (419)530-8295



  

Reply via email to