There is not necessarily anything unusual about this. If the generators are 
relatively expensive and their PMIN value is zero, it may be economical to 
dispatch them at 0 MW output.

    Ray


> On Jun 9, 2017, at 8:15 PM, Xinwen Ni <xinwen...@strath.ac.uk> wrote:
> 
> Hi, all
> 
> I built a test system based on MOST tutorial 7 and ran into a problem. Even 
> though generators are scheduled online as indicated in mdo.UC.CommitSched. 
> The outputs of some generators are returned zero in 
> mdo.results.ExpectedDispatch.
> Please let know me if you have any clue. Thank you.
> 