Each offer corresponds to a generator and each bid corresponds to a 
dispatchable load in the underlying power grid. So, if you want to change the 
number of schedulable loads, you will have to add dispatchable loads as new 
rows in the gen matrix in the case file as well as adding rows to the bid 
inputs.

Hope this helps,

   Ray

P.S. And, yeah, please don’t try to send attachments to this list, especially 
not the MATPOWER distribution which anyone can easily download from the website.



On Oct 19, 2021, at 3:45 AM, 2254878263 <jh...@qq.com<mailto:jh...@qq.com>> 
wrote:

Sorry, the email keeps reminding you that you can't send more than 1m files


------------------ 原始邮件 ------------------
发件人: "MATPOWER discussion forum" 
<engr.mwaqar6...@gmail.com<mailto:engr.mwaqar6...@gmail.com>>;
发送时间: 2021年10月19日(星期二) 中午11:20
收件人: "MATPOWER discussion 
forum"<matpowe...@list.cornell.edu<mailto:matpowe...@list.cornell.edu>>;
主题: Re: question about smartmarket

Hi. Can you send me the unzip folder of matpower7.1 so that i can myself check 
the report error. I will surely ask in the discussion forum then, what to do 
next.
Thank You.

On Mon, 18 Oct 2021 at 13:43, 2254878263 <jh...@qq.com<mailto:jh...@qq.com>> 
wrote:
Hi all
I am learning to use smartmarket of Matpower 7.1 to calculate electricity 
price. I want to change the number of schedulable loads in the manual routine, 
but the program keeps reporting errors. So ask how to change load bits.Plaese 
help me.

Thank you very much.