I would do something like this in Advance option: 
http://www.mypicx.com/11172009/Flags/
Of course, you need to set Action Filter to 'All'

Bojan

On 17 нов, 06:57, Aditya <[email protected]> wrote:
> How to set up a view that will show completed tasks in the same view
> as active tasks
>
> I want to view tasks that I have due today by flag.
> I also do not want tasks that I click complete today, not to vanish
> from this view. So that I have a view to what was planned and what is
> completed, in the same view.
>
> What is the filter that needs to be created for this?
>
> thanks
> Aditya

--

You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/mylifeorganized?hl=.