I think you're right to ask for this. Fixed lead time is one scheduling concept i.e. if I need to finish by a certain time I need to start at a certain time OR if I start at a certain time it means I'll finish at a certain time. However, another scheduling concept which needs to be accommodated is "start not before" and "finish not after", which is date driven and does not lend itself to fixed lead time calculation. As you say, this is especially true where time is involved.
-- You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To view this discussion on the web visit https://groups.google.com/d/msg/mylifeorganized/-/-oxcgKwLiBoJ. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/mylifeorganized?hl=en.