I do as TMZ suggests and use Min Time and Max Time as costs, and this can 
be summed to the parent if the Parent is a Project.  Beware, one needs to 
enter a H after the input for example 15 h, else it thinks its minutes and 
will have 45  plus 30 = 1 hour and 15 minutes

On Saturday, August 3, 2019 at 3:13:56 PM UTC-5, TMZ wrote:
>
> In "setup colums" (right from the search bar) you can see every option you 
> can setup as an column. Cost value isn't there, but you could take "time 
> required" as costs.
>

-- 
You received this message because you are subscribed to the Google Groups 
"MyLifeOrganized" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to mylifeorganized+unsubscr...@googlegroups.com.
To view this discussion on the web visit 
https://groups.google.com/d/msgid/mylifeorganized/87fe0295-f844-469b-8deb-2a40f18adf11%40googlegroups.com.