and none in the other two facilities you operate in that same building had any 
failures. 




----- 
Mike Hammett 
Intelligent Computing Solutions 

Midwest Internet Exchange 

The Brothers WISP 

----- Original Message -----

From: sro...@ronan-online.com 
To: "Mike Hammett" <na...@ics-il.net> 
Cc: "NANOG" <nanog@nanog.org> 
Sent: Monday, January 15, 2024 9:14:49 AM 
Subject: Re: "Hypothetical" Datacenter Overheating 



I’m more interested in how you lose six chillers all at once. 


Shane 



On Jan 15, 2024, at 9:11 AM, Mike Hammett <na...@ics-il.net> wrote: 




<blockquote>


Let's say that hypothetically, a datacenter you're in had a cooling failure and 
escalated to an average of 120 degrees before mitigations started having an 
effect. What are normal QA procedures on your behalf? What is the facility 
likely to be doing? What should be expected in the aftermath? 




----- 
Mike Hammett 
Intelligent Computing Solutions 

Midwest Internet Exchange 

The Brothers WISP 


</blockquote>

Reply via email to