Where are you seeing that kind of pricing? The utility cost would have to be 
sub $0.15/kWh to even pay the bill with 20kW, ignoring any cooling.



Thanks,




Riley C. O'Connor
[email protected] // m32.io



[Tel&Signal] 307.438.9253 
[Social]     LinkedIn | Twitter | GitHub
[PGP]        E017 B967 AC29 E321




On Wednesday, December 11th, 2024 at 12:40 PM, Aaron Wendel 
<[email protected]> wrote:

> Considering a full cabinet with 20kW in the US costs under $2k total I would 
> say so.
> 

> Aaron
> 

> 

> 

> ------ Original Message ------
> From "Tony Wicks" <[email protected]>
> To "'Aaron Wendel'" <[email protected]>
> Cc "'harbor235'" <[email protected]>; "'NANOG list'" <[email protected]>
> Date 12/11/2024 1:08:37 PM
> Subject RE: COLO space in EU
> 

> 

> > Yea, looks like whoever did that quote does not really want the business 
> > and is pricing it as such
> > 

> > From: NANOG <[email protected]> On Behalf Of Aaron 
> > Wendel
> > Sent: Thursday, 12 December 2024 8:05 am
> > To: harbor235 <[email protected]>; NANOG list <[email protected]>
> > Subject: Re: COLO space in EU
> > 

> > So they have a charge just to have the capacity present of 7000 euros/month 
> > and then .278 euros per KWh on top of that?
> > 

> > I wish I could get away with charging that.
> > 

> > Aaron
> > 

> > ------ Original Message ------
> > 

> > From "harbor235" <[email protected]>
> > 

> > To "NANOG list" <[email protected]>
> > 

> > Date 12/11/2024 12:45:52 PM
> > 

> > Subject COLO space in EU
> > 

> > > Hi all,
> > > 

> > > Looking for colo space in Amsterdam, is it common to have to pay for 
> > > phase3 power busbar and busbar, power supply, and tap off? Total costs 
> > > for adding 3 phase plus testing etc ..... 136.000 Euros for NRCs and the 
> > > following MRC:
> > > 

> > > The Service Fee for a 20kW deployment would be €350/kW/month, so €7,000 
> > > per month in total based on a 36 month term and 3% annual indexation
> > > 

> > > · Electricity consumption will be measured and invoiced monthly in 
> > > arrears at €0.278 per kWh (2024 pricing)
> > > 

> > > Mike

Attachment: signature.asc
Description: OpenPGP digital signature

Reply via email to