Thierry Carrez wrote: > Kilo Design Summit: Nov 4-7 > Kilo-1 milestone: Dec 11 > Kilo-2 milestone: Jan 29 > Kilo-3 milestone, feature freeze: March 12 > 2015.1 ("Kilo") release: Apr 23 > L Design Summit: May 18-22
Following feedback on the mailing-list and at the cross-project meeting, there is growing consensus that shifting one week to the right would be better. It makes for a short L cycle, but avoids losing 3 weeks between Kilo release and L design summit. That gives: Kilo Design Summit: Nov 4-7 Kilo-1 milestone: Dec 18 Kilo-2 milestone: Feb 5 Kilo-3 milestone, feature freeze: Mar 19 2015.1 ("Kilo") release: Apr 30 L Design Summit: May 18-22 If you prefer a picture, see attached PDF. -- Thierry Carrez (ttx)
kilo.pdf
Description: Adobe PDF document
_______________________________________________ OpenStack-dev mailing list OpenStack-dev@lists.openstack.org http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev