Thanks, Brady.  Sorry I missed your previous mail.

MS9 and 10 are offsets of the release, so if the release date is changed,
then MS9 and 10 will change, accordingly.

David


On Thu, Mar 23, 2017 at 2:11 AM, Brady Allen Johnson <
brady.allen.john...@ericsson.com> wrote:

>
> David,
>
> I asked in an email previous to this the following questions:
>
> Considering the Danube 1.0 release will be delayed by at least 1 week,
> what is the status of Milestones 9 and 10?
>
> Milestone 9 is due today, March 22 and requires us to have all the JIRAs
> closed and/or assigned to subsequent releases. Does this still make sense
> if we will still be working on fixing problems?
>
> Milestone 10 is due on Friday, March 24. This probably makes more sense to
> maintain, but then we might have MS10 before MS9.
>
>
> Brady
>
> -----Original Message-----
> *From*: David McBride <dmcbr...@linuxfoundation.org
> <david%20mcbride%20%3cdmcbr...@linuxfoundation.org%3e>>
> *To*: TECH-DISCUSS OPNFV <opnfv-tech-discuss@lists.opnfv.org
> <tech-discuss%20opnfv%20%3copnfv-tech-disc...@lists.opnfv.org%3e>>,
> opnfv-project-leads <opnfv-project-le...@lists.opnfv.org
> <opnfv-project-leads%20%3copnfv-project-le...@lists.opnfv.org%3e>>
> *Cc*: TSC OPNFV <opnfv-...@lists.opnfv.org
> <tsc%20opnfv%20%3copnfv-...@lists.opnfv.org%3e>>
> *Subject*: [opnfv-tech-discuss] [release][danube] Danube release status
> *Date*: Wed, 22 Mar 2017 11:27:25 -0700
>
> Team,
>
> As you may be aware, the TSC determined on Tuesday that they do not have
> enough information to vote on the Danube 1.0 release.  Therefore:
>
>    - The vote on the release will be deferred to the next TSC meeting on
>    Tues, March 28
>    - This means that we are no longer planning to release on Mon, March
>    27, as originally planned.
>    - A revised schedule for release will be developed based on input from
>    scenario owners and test framework PTLs.
>    - The Release Manager will poll the scenario owners and test framework
>    PTLs to assess the confidence level for releasing with different schedule
>    offsets.
>
> I will update this thread as I gather additional data and decisions are
> made.  In the mean time, please continue to work hard toward the release,
> as I know you are.
>
> Let me know if you have questions or concerns.
>
> David
>
> --
> *David McBride*
> Release Manager, OPNFV
> Mobile: +1.805.276.8018
> Email/Google Talk: dmcbr...@linuxfoundation.org
> Skype: davidjmcbride1
> IRC: dmcbride
>
> _______________________________________________
> opnfv-tech-discuss mailing 
> listopnfv-tech-discuss@lists.opnfv.orghttps://lists.opnfv.org/mailman/listinfo/opnfv-tech-discuss
>
>


-- 
*David McBride*
Release Manager, OPNFV
Mobile: +1.805.276.8018
Email/Google Talk: dmcbr...@linuxfoundation.org
Skype: davidjmcbride1
IRC: dmcbride
_______________________________________________
opnfv-tech-discuss mailing list
opnfv-tech-discuss@lists.opnfv.org
https://lists.opnfv.org/mailman/listinfo/opnfv-tech-discuss

Reply via email to