Thanks Ton,

Ideally what would be good is to set a new end time after it has been started - 
this would also be beneficial if we had to extend the downtime window instead 
of shorten it.

Matt

From: [email protected] 
[mailto:[email protected]] On Behalf Of Ton Voon
Sent: 06 January 2010 22:30
To: Opsview Users
Subject: Re: [opsview-users] Modifying Scheduled Downtime

Hi Matt,

On 6 Jan 2010, at 20:23, Matt White wrote:


This may already exist in Opsview I just havent found it yet but...

If i schedule downtime for a particular hostgroup that contain a large number 
of devices for a 3 hr maintenance window but I end up only taking 1hr to 
complete the work is there a way to reschedule the end of the downtime period 
once it is set? The reason being I would let the rest of my team know the work 
has been completed early and want Opsview to begin notifying again after the 
completion without having to delete the downtime period.

Is this possible at the moment/something that is planned for the future?

If you click on the downtime icon at the host group level, it lists all the 
downtime. You can then select cancel to cancel all the downtime. This 
effectively means that the downtime has finished early.

However, I've just thought that you cold end up cancelling downtime in the 
future too, so we may have to make an adjustment to how that works.

Ton