Yes, and the outage was only five hours. From about 2015-05-29 18:30 PT to about 23:30 PT, on a Friday. (Not until 21:30, as originally promised.)
Also, it was a "limited issue", according to HE. Not sure what that means -- it looks like the whole Linode network in Fremont has been down, plus some other customers, too, even though supposedly only one out of the eight power generators was affected. Did anyone NOT have had their server power-cycled? IIRC, this is by far not the first power-related issue over in Fremont. In other words, business as usual! C. On 30 May 2015 at 17:39, Alex Rubenstein via Outages <outages@outages.org> wrote: > So the outage was OK to have since they had staff on site? > > On May 30, 2015 09:01, Paul WALL via Outages <outages@outages.org> wrote: > > It's a good thing Hurricane Electric had electricians on site to deal > with the outage. > > If it were an Equinix or Telx site, the response would have assuredly > been far worse. > > Paul > _______________________________________________ > Outages mailing list > Outages@outages.org > https://puck.nether.net/mailman/listinfo/outages > > > _______________________________________________ > Outages mailing list > Outages@outages.org > https://puck.nether.net/mailman/listinfo/outages _______________________________________________ Outages mailing list Outages@outages.org https://puck.nether.net/mailman/listinfo/outages