On 7 March 2012 10:36, John R Pierce <[email protected]> wrote:
> On 03/06/12 3:31 PM, Ondrej Ivanič wrote:
>>
>> - one side completely down: Client should use switch to other side
>> transparently (Failover / High Availability)
>
>
> what happens if the link between the sites is down and both sides decide
> they are master?  then how do you put the pieces back together ?

Good catch! From application point of it is quite easy to sync data
between sites. Let's assume that writes should be disabled in this
scenario.

-- 