Hi,
It's the milestone week - 4.13 M1.
Monday: Last day of development (and even then, no "big changes").
After Monday 18:00 ET, no feature work or unrelated fixes are
allowed -- only regression fixes.
Tuesday: All-day test pass. Nobody should develop or fix anything.
Literally spend the entire day testing.
Wednesday: Fix day with a focus on fixing regressions found during
the test day (Tuesday). No unrelated fixes. Review and thoroughly
test all commits.
The last Wednesday build is the release candidate every team
signs off on Thursday.
The "New and Noteworthy" entries are due on Wednesday evening:
Git repo:
ssh://git.eclipse.org/gitroot/www.eclipse.org/eclipse/news.git
Gerrit:
ssh://git.eclipse.org:29418/www.eclipse.org/eclipse/news.git
Live website: https://www.eclipse.org/eclipse/news/4.13/
Thursday: Sign-off after re-testing, or at least confirming no
changes have been made to your component's code since the last
time the component was tested well.
Friday: Build is officially declared and made available.
The master branch stays closed until the milestone is officially
released. (That is, it is not enough that your component has
signed off.)
Thanks & Regards,
Sarika
_______________________________________________
platform-dev mailing list
[email protected]
To change your delivery options, retrieve your password, or unsubscribe from
this list, visit
https://www.eclipse.org/mailman/listinfo/platform-dev