Hi all,

Next week is the milestone week for 4.14M1.

Monday: Last day of development (and even then, no "big changes"). After
Monday 18:00 ET, no feature work or unrelated fixes are allowed -- only
regression fixes.
Tuesday: All-day test pass. Nobody should develop or fix anything.
Literally spend the entire day testing.
Wednesday: Fix day with a focus on fixing regressions found during the test
day (Tuesday). No unrelated fixes. Review and thoroughly test all commits.
The last Wednesday build is the release candidate every team signs off on
Thursday.
The "New and Noteworthy" entries are due on Wednesday evening:

Git repo: ssh://git.eclipse.org/gitroot/www.eclipse.org/eclipse/news.git
Gerrit: ssh://git.eclipse.org:29418/www.eclipse.org/eclipse/news.git
Live website: https://www.eclipse.org/eclipse/news/4.13/
Thursday: Sign-off after re-testing, or at least confirming no changes have
been made to your component's code since the last time the component was
tested well.
Friday: Build is officially declared and made available.
The master branch stays closed until the milestone is officially released.
(That is, it is not enough that your component has signed off.)
                                                         
 Note: India team will begin testing on Wednesday due to 
 Tuesday being off.                                      
                                                         



Thanks & Regards,
Vikas
_______________________________________________
platform-dev mailing list
platform-dev@eclipse.org
To change your delivery options, retrieve your password, or unsubscribe from 
this list, visit
https://www.eclipse.org/mailman/listinfo/platform-dev

Reply via email to