We are scheduled to promote and contribute 4.18 RC1 to the simrel on Friday
the 27th.

Here is the schedule:

Wednesday 25 Oct -- API and feature freeze, Release Candidate build

Thursday 26 Oct -- Bug verification and Sign-off 4.17 RC1

Friday 27 Oct -- 4.17 RC1 Promotion and contribution to SimRel

Please note the following excerpt from the freeze plan:

RC1

All fixes submitted must have a project lead or PMC vote on the bug report,
and the fix must be reviewed by an additional committer (any committer
other than the one who made the fix). A positive review from a project lead
or PMC member means implicit approval and no vote is needed on the bug
report. Ongoing changes to documentation, tests or examples do not require
approval.