Fermi - annual requal Benjy Bertossi Fermi2 - RP Supervisor 734-586-4935 [email protected]
From: "Bebb, Jeremy L." <[email protected]> To: "[email protected]" <[email protected]> Date: 05/18/2011 10:33 AM Subject: Powernet: SCBA demonstration requal Sent by: [email protected] Cooper Nuclear poses the following question: CNS is currently accessing our Don and Remove SCBA qualification for requalification requirements. Currently we have an initial qualification that requires the user to demonstrate their ability to don and remove the unit with no requalification required. What is your plant’s process for this qualification? Is it a one-time qual or do you have a re-qual frequency (annually, etc)? Thanks, Jeremy Bebb Staff Health Physicist Cooper Nuclear Station (402) 825-5026